This week saw the setup of the earthworks, ready for a slab pour which was originally scheduled for Thursday 1/12. Unfortunately, the rain over the weekend caused delays at other jobs for the concreters, so we got pushed back to Tuesday 6/12.
Leanne jumped the gun a bit and posted some pictures of the plumbing and formwork in the post below, so I won't double up on them here.
Monday 28/11:
Under slab plumbing installed.
Thursday 1/12:
Slab excavation complete, formwork started. Reo and Waffle pods delivered to site.
Friday 2/12:
Slab boxing complete.
Completed slab framework |
Plan for next week:
Reo and waffle pods laid
Slab poured
Electricity meter box fitted
Framing started
Progress is a good thing. Hope u get ur slab poured this week.
ReplyDeletePls update us with ur progress posts coz I will be a regular reader.